Construction | Capital Project Word of the Week - February 2021

February 1, 2021
Fabrication & Construction

Disclaimer: All images are Creative Commons licensed and are intended to represent the current industry. They are not the property of H+M Industrial EPC.

published by
Archie Alexander
VP of Project Execution

Thank you for your interest in our content.

All you need to provide is your email and you'll get instant access to this content.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Thank you for your interest in our content.

All you need to provide is your info & email and you'll get instant access to this content.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Capital Project Word of the Week - Construction

Thank you for visiting our Capital Project Word of the Week website feature. Our theme this month is Construction. We hope this provides you with some meaningful information about our industry and the services we provide. Each week we will be adding a new Word of the Week to the page. Come back frequently to see our new additions!

Week of February 22, 2021

Construction Work Plan

[kuhn-struhk-shuhn ] [ work ] [ plan ]

To many project related personnel, the Level III Project schedule represents the most granular vision of the documented execution plan for the successful delivery of a Project.  A Construction Work Plan is the mechanism through which construction translates the Level III schedule activities into small pieces of work, details the work to be completed in a given period of time, and communicates the number of personnel required to achieve the work plan.

 

A Level III schedule is typically detailed at an area and discipline level.  For example, a Level III schedule activity for piping installation may be – “Install FW Piping in Area 100.”  A construction work plan may hone this Level III schedule activity to a definition similar to – “Erect, Weld, and Support100% of Isometric 123, using 4 piping personnel, a crane operator, to be complete this week.”  The process of creating a Construction Work Plan not only refines the detail of Level III schedule activities, but it also integrates critical requirements for successful execution including, but not limited to, materials, personnel, construction equipment, scaffolding, and coordination with third parties to support successful plan execution.  

Word of the Week referrals will be entered into a monthly raffle. Every referral is an entry. Good luck and share on! Click here to refer your colleagues for Word of the Week updates.

Subscribe to our newsletter below to get weekly Word of the Week updates! Have a word suggestion? Send your suggestions to wow@hm-ec.com.

---

Week of February 1, 2021

Hydrostatic Leak Test

[hahy-druh-stat-ik ] [ leek ] [ test ]

A Hydrostatic Leak Test commonly referred to as a “hydro-test,” is a non-destructive examination method used to ensure tightness (verify integrity) of a container.  In Industrial Construction ,hydro-testing is required by design codes. Owner specifications may also expand the requirements above and beyond the code minimum requirements.  A hydro-test is typically conducted using clean water, however other sources such as firewater or seawater may be used depending on the application.  During a hydro-test, the container is filled with water, then additional pressure may be added to a closed container (such as piping) utilizing a pump, and finally, the pressure is maintained for a specified period of time.  A pressure drop is the typical way a leak is found, but for open-top containers, such as tanks, leaks would typically be found through a visual examination.

 

The most widespread hydro-testing performed in our business is on piping systems, which are routinely governed by ASME B31.3 or B31.4 design codes.  The test pressure requirements typically range from 1.0x the operating pressure up to 1.5x the design pressure of the piping.  The amount of time the pressure is maintained typically ranges from 10 minutes, up to 8 hours, but may be longer in certain circumstances.

 

Hydro-testing is largely considered to be the safest method of pressure testing, due to water's unique characteristic as a nearly incompressible fluid.  The inherent dangers of pressure testing with a compressible gas, such as air, are due to the compressible and therefore expansive nature of the same under failure.

Week of February 8, 2021

Constructability

[kon-struhkt - uh-bil-i-tee ]

Constructability is the process through which we insert construction knowledge and experience into the earlier lifecycle phases of a Project.  This is done to incorporate construction considerations in the planning, layout, design, and procurement of a project to optimize, or better enable, overall project execution success and field delivery.

Success in a constructability program may be measured by HSE improvements, increased quality, reductions in costs, and fewer schedule delays amongst other measurables.

 

Key example considerations in the constructability process may include:

·        Simplified and Standardized Design

·        Construction Technologies

·        Modular or Pre-Assembly Designs

·        Operations Driven Schedule

·        Accessibility

·        Specifications and Procedures

·        Weather Considerations

The highest ability to influence project cost is during conceptual engineering and design.  As a project advances, this ability decreases, and the opportunity to incorporate construction experience into these phases decreases as well. Constructability is a continuous process of learning and development, with the vision of perpetually getting better!

Week of February 15, 2021

Mechanical Completion

[muh-kan-i-kuhl ] [ kuhm-plee-shuhn ]

Many industrial construction projects end for the Contractor at Mechanical Completion.  The contract and schedule are satisfied at this critical milestone.  Mechanical Completion is when construction has completed the work, in accordance with the contract to the extent required for the Client to begin commissioning activities.  In most cases, the only remaining construction work performed after Mechanical Completion will be minor punch list work that does not interfere with start-up. Some examples of those items include paint touch up, site cleanup, tagging of items, scaffold removal. etc.

 

Mechanical Completion may be simply defined as the end of the construction phase of a Project.  Post-construction phases typically include commissioning, which may be broken down further into a pre-commissioning phase.  At the end of the commissioning phase, the project is ready for start-up and subsequently, operation.

About the Author
Archie has 18+ years of industrial EPC experience in the Refining, Petrochemical and LNG industries. He has worked on projects across four continents, through widely varying conditions with multiple nationalities and languages. His responsibilities ranged from Field Engineering on maintenance projects to the Construction Management of new power and utility units comprising 5,000,000 man-hours and 1,000 craft personnel. His experience includes the review and development of SOW and contract documents, constructability input through FEED and detail design, construction estimate and schedule development, and Level 4 construction execution planning. Previous experience includes 15+ years at CB&I.

Want to Learn More About Project Management?

To find out more about the advantages and disadvantages of turnkey projects and how H+M Industrial EPC can meet your capital project needs, contact us through our website today.

To find out more about the advantages and disadvantages of turnkey projects and how H+M Modular can meet your capital project needs, contact us through our website today.

Contact Us
The logo for H+M
The H+M Industrial Team

For over three decades, we have provided best-in-class capital project management services to Energy and Chemical industries through our proven EPC approach. We are dedicated to providing trust, experience, and efficiency through all stages of engineering, procurement, and construction--on budget and on time.

Partnering with H+M Modular

H+M Modular, a division of H+M Industrial EPC, specializes in custom fabricated equipment, modules, and skids for energy and chemical industries. The approach emphasizes the potential for decreased risk through more controlled fabrication, leading to enhanced quality and safety, reduced labor costs and construction times, improved labor availability, and solutions to geographic challenges. We are dedicated to providing trust, experience, and efficiency through all stages of traditional and modular construction projects using our proven EPFC approach, If you're considering modular fabrication, we invite you to connect with us to learn about how modular solutions can improve project outcomes.

Stay Informed – Join our Newsletter.

Get announcements, insights, and white papers directly in your inbox.
Sign Up Success!
You should start receiving our newsletter in your inbox now. We promise we won't spam you or sell your data.
Oops! Something went wrong while submitting the form.