Front-end loading (FEL), also known as front-end planning (FEP), is a highly valuable process in the capital project life cycle that, if well-executed, can greatly improve project success. It includes the development of strategic information and key documentation necessary for project owners to address potential project risks, decide whether or not to move forward with the project and commit resources, and maximize the potential for project success.
FEL consists of three distinct phases:
- FEL 1: Opportunity Identification and Assessment
- FEL 2: Scope Development and Conceptual Engineering
- FEL 3/Front-End Engineering Design (FEED): Execution Planning and Basic Engineering
If utilized as a formal stage gate process, FEL can be used as an approval process with gates after each phase to allow key stakeholders to make informed decisions regarding investments. Each gate must be passed before proceeding to project execution. Individual phases of FEL, such as FEL3/FEED, can also be performed standalone depending on the level of planning required for a given capital project.
According to CII, FEL can produce significant value for project owners, providing benefits such as the following:
- Increased schedule and cost predictability.
- A reduced probability of project failures.
- Improved operational performance.
- Better achievement of business goals.
- Fewer changes to the project scope.
Aside from producing a robust scope definition and highly accurate cost estimate, FEL produces a breadth of valuable deliverables that can be referenced and leveraged throughout the entire project life cycle. Here is a look at some of the most common FEL deliverables you are likely to encounter.
Common FEL Deliverables for Capital Projects
Every capital project is unique; consequently, FEL deliverables are likely to vary a bit from project to project depending on the project scope, provided items, project drivers, project characteristics and risk profiles, and of course, client requirements. Common FEL deliverables by phase are detailed below.
Standard FEL 1 Deliverables
Typically <5% of Eng cost - TIC Estimate +/- 50%
Preliminary:
Overall
- Justification
- Scope of Work
- Project Schedule (level 2)
- Infrastructure Review (power, utilities, etc.)
- Total Installed Cost (TIC) Estimate
Process
- Process Flow Diagrams (PFDs, block flow)
- Heat and Material Balance (H&MB)
Mechanical/Piping
- Plot Plan
- Major Equipment List
Instrumentation and Electrical
- Control Philosophy
- Instrument List
- Location Plans
- Area Classification Review
Early/Optional FEL 1 Deliverables
- Process Design Basis
- Identification/Evaluation of Licensing Technology
- Preliminary HSE Guidelines
- General Quotes
- Standards and Specifications
- Tie-In Photos
- Foundation and Structural Support Sketches
- Civil/Structural Layout
- Constructability Review
Standard FEL 2 Deliverables
Typically 5-10% of Eng. Cost TIC Estimate +/- 20% to 30%
Preliminary:
Overall
- Scope of Work
- Project Schedule (level 2)
- TIC estimate
Process
- Block Flow Diagram
- Piping and Instrumentation Diagram (P&ID)
- Process Drawing List
- Utility Consumption
Mechanical/Piping
- Plot Plan
- Equipment Arrangement Plan
- Utility Requirements
- Major Line Routing Schematic
- Line Test
- Tie-In List
- Major Equipment Calculations
- Major Equipment Process Data Sheets
- Major Equipment List
- Initial Quotes for Major Equipment
Civil/Structural
- Foundation Location Plan
- Foundation/Steel Sketches
- Existing Soil Analysis
Instrumentation and Electrical
- Single-Line Diagrams (SLDs)
- Instrument List
- Major Electrical Equipment List
- Control System Philosophy
- Plans
- Motor List
Issued for Design (IFD):
Process
- PFD
- Heat and Material Balance (H&MB)
Early/Optional FEL 2 Deliverables
- 3D Scan
- 3D Model
- Hazard Analysis
- Flare Load Summary
- Sewer System Definition
- Environmental Assessment Plan
- List of Proposed Licensors
- Updated Design Basis
- Piping Stress Analysis
- Probing Drawings
- Existing Support Analysis
- Safety Control System
- Constructability Review
Standard FEL 3/FEED Deliverables
Typically 10-20% of Eng. Cost - TIC Estimate +/- 10% to 15%
Preliminary:
Overall
- Scope of Work
- Project Schedule (level 2)
- TIC Estimate
Process
- Pressure Safety Valve (PSV) Sizing
Civil/Structural
- Structural Design and Analysis/Sketches
- Building Plans and Elevation
Instrumentation and Electrical
- Distributed Control System (DCS) I/O count
- Spec Sheets
Issued for Design (IFD):
Process
- PFDs
- Block Flow Diagram
- H&MB
- Process Drawing List
- P&ID
- Hydraulic Study
Mechanical/Piping
- Plot Plan
- Equipment Arrangement Plan
- Utility Requirements
- 3D Model/Piping Plans
- Line List
- Tie-In List
- Tie-In Location Plan
- Global Material List
- Major Equipment List
- Purchase-Ready Equipment Data Sheets
- Major Equipment Process Data Sheets
- Outline Drawings
- Bid Tab for Major Equipment
- Vendor Data Sheets
Civil/Structural
- Foundation Location Plan
- Foundation Sketches
- Steel/Concrete Estimation
Instrumentation/Electrical
- SLDs
- Instrument Index
- Major Electrical Equipment Details
- Block Diagrams
- Electrical Area Classification (EAC) Plans
- Cause and Effect (Hazard and Operability Analysis (HAZOP))
- Motor List
Early/Optional FEL 3/FEED Deliverables
- 3D Laser Scan
- 3D Model
- Hazard Analysis
- Flare Load Summary
- Sewer System Definition
- Operating Guidelines
- HAZOP Report
- Updated Design Basis
- PSV Distribution Study
- Equipment Insulation Requirements
- Equipment Specification Sheets
- Demolition Drawings
- Piping Insulation Schedule
- Fire Water System Design
- Process Sewer System
- Pipe Support Details
- Pipe Stress Analysis
- New Soil Study
- Contaminant Calculations
- Safety Control System
- Identify Substation, Transformer, or Feeder Needs
- Constructability Review
H+M Industrial EPC: Delivering Leading Front-End Planning Services
Whether your capital project requires a formal stage gate process, or you are looking to determine the minimum information requirements for an EPC proposal, H+M Industrial EPC’s strategic, client-oriented front-end planning services support you in making the best investment decision possible. Our in-house tools, resources, capabilities, and experience planning capital projects help guide you to the best project decisions.
Want to Learn More About Project Management?
Download HereThe H+M Industrial Team
For over three decades, we have provided best-in-class capital project management services to Energy and Chemical industries through our proven EPC approach. We are dedicated to providing trust, experience, and efficiency through all stages of engineering, procurement, and construction--on budget and on time.
Partnering with H+M Modular
H+M Modular, a division of H+M Industrial EPC, specializes in custom fabricated equipment, modules, and skids for energy and chemical industries. The approach emphasizes the potential for decreased risk through more controlled fabrication, leading to enhanced quality and safety, reduced labor costs and construction times, improved labor availability, and solutions to geographic challenges. We are dedicated to providing trust, experience, and efficiency through all stages of traditional and modular construction projects using our proven EPFC approach, If you're considering modular fabrication, we invite you to connect with us to learn about how modular solutions can improve project outcomes.