The project scope included:
- Installing vault pipes in four different manifold vaults and piping installation to tie-in the vaults.
- Installing three horizontal pumps and three vertical pumps, aboveground tie-in pipe to the ship dock pipe rack, and underground pipe from the main vault to the pumps.
- +450 bolt ups, including several Twin Seal valves, 9,200LF of aboveground pipe, and +2,000LF of underground pipe.